Laytime & Demurrage Calculator
A quick, indicative laytime statement for charterers, owners, operators and trading houses: laytime allowed, every period counted or excluded, and the time on demurrage or despatch.
The arithmetic is never the hard part. Results depend on how the charter party is read and on the quality of the SOF. A clean, complete, protested SOF wins claims more often than any calculator.
Charter party terms
Port call (from the SOF)
Result
Time basis: local port time, as enteredTimes are used exactly as entered, in local port time, with no daylight-saving adjustment. If the clocks change during the call, adjust the entries by the hour.
Payable by charterer to owner at US$18,000.00/day pro rata.
- Laytime allowed
- 5d 12h 00m (5.5000 d)
- Loading: laytime commenced
- Mon 02.11.2026 12:30
- Loading: laytime expired
- Tue 10.11.2026 04:30
- Loading: completed
- Tue 10.11.2026 16:00
- Laytime used
- 5d 12h 00m (5.5000 d)
- Time on demurrage
- 0d 09h 30m (0.3958 d)
- Despatch time
- 0d 00h 00m (0.0000 d)
Laytime statement, period by period
All times local port time · durations d/h/m| From | To | Period | Duration | % counted | Time counted | Running total |
|---|---|---|---|---|---|---|
| Mon 02.11.2026 06:30 | Mon 02.11.2026 12:30 | Turn / notice time 6h (not counted) | 0d 06h 00m | 0% | 0d 00h 00m | 0d 00h 00m |
| Mon 02.11.2026 12:30 | Tue 03.11.2026 14:00 | Laytime running | 1d 01h 30m | 100% | 1d 01h 30m | 1d 01h 30m |
| Tue 03.11.2026 14:00 | Tue 03.11.2026 20:00 | Rain, loading suspended (weather working day) | 0d 06h 00m | 0% | 0d 00h 00m | 1d 01h 30m |
| Tue 03.11.2026 20:00 | Thu 05.11.2026 09:00 | Laytime running | 1d 13h 00m | 100% | 1d 13h 00m | 2d 14h 30m |
| Thu 05.11.2026 09:00 | Thu 05.11.2026 13:00 | Shiploader breakdown (shore side), half time | 0d 04h 00m | 50% | 0d 02h 00m | 2d 16h 30m |
| Thu 05.11.2026 13:00 | Sat 07.11.2026 12:00 | Laytime running | 1d 23h 00m | 100% | 1d 23h 00m | 4d 15h 30m |
| Sat 07.11.2026 12:00 | Mon 09.11.2026 08:00 | Excluded period (SHEX) | 1d 20h 00m | 0% | 0d 00h 00m | 4d 15h 30m |
| Mon 09.11.2026 08:00 | Tue 10.11.2026 04:30 | Laytime running | 0d 20h 30m | 100% | 0d 20h 30m | 5d 12h 00m |
| Tue 10.11.2026 04:30 | Laytime expires: vessel on demurrage | 5d 12h 00m | ||||
| Tue 10.11.2026 04:30 | Tue 10.11.2026 08:00 | On demurrage | 0d 03h 30m | 100% | 0d 03h 30m | 5d 15h 30m |
| Tue 10.11.2026 08:00 | Tue 10.11.2026 10:00 | Shifting berth (excluded by CP, applies on demurrage) · on demurrage | 0d 02h 00m | 0% | 0d 00h 00m | 5d 15h 30m |
| Tue 10.11.2026 10:00 | Tue 10.11.2026 16:00 | On demurrage | 0d 06h 00m | 100% | 0d 06h 00m | 5d 21h 30m |
Flags: what could change this result
- Loading: NOR tendered at 06:30, outside usual office hours (08:00–17:00). Check the CP's NOR clause.
- Loading: an exception is set to apply after demurrage. Only do this if the CP wording clearly covers time on demurrage.
- Laytime expired: exceptions stop applying from that moment (once on demurrage, always on demurrage) unless flagged.
- NOR validityTendered early, before free pratique or customs clearance, or vessel not ready? Check WIBON / WIPON / WIFPON / WICCON wording and whether NOR was accepted or re-tendered.
- Turn / notice timeDoes the CP give a fixed number of hours, or the next working period? Does it apply when the vessel is already on demurrage?
- SHEX and holidaysExact excluded hours (e.g. Saturday 12:00 to Monday 08:00), the port's official holidays, and whether 'unless used' counts actual or full time.
- Weather, strikes, shifting, breakdownsWeather working day vs. weather actually stopping work, half-rate clauses, shifting between berths, shore vs. ship breakdowns.
- Once on demurrageExceptions usually stop applying once laytime expires unless the clause expressly covers demurrage.
- SOF qualityMissing, conflicting or vague entries, unsigned or protested SOFs, and missing Letters of Protest weaken any claim.
- Time barsMany CPs require the claim and full supporting documents within a set period (e.g. 90 days). Late or incomplete claims can be lost entirely.
- Clock changesTimes are used exactly as entered, in local port time, with no daylight-saving adjustment. If the clocks change during the call, adjust the entries by the hour.
- CP vs. sale contractThe charterer recovers from the seller or buyer under the sale contract. Laytime terms, rates and time bars there may not match the CP.
Need a second pair of eyes?
Leman Maritime can review your SOF, NOR and CP clauses and prepare a supported laytime statement. Contact: leman@lemanmaritime.com
Contact usIndicative only. Not legal advice or a final claim figure; check against the full CP, sale contract and supporting documents. Leman Maritime accepts no liability for decisions based on this tool.
Please anonymise your data (‘Vessel A’, ‘Charterer X’). Nothing you enter is stored or sent anywhere: the calculation runs entirely in your browser and is cleared when you close the page.